Proactive Optimised Assets and Practices

Cross Factor

Project Data

Start date:

01/11/2026

End date:

31/12/2027

Budget:

£336,812

Summary

Cross Factor will provide a quicker, simpler and more affordable way to connect to the 132kV network. Using a branch joint instead of a traditional GIS substation will mean fewer civil works, reduced outages and shorter delivery times, helping the network expand to support Net Zero.

What is the project about?

Demand for connections to the 132kV network is growing as more renewable energy connects to the network and more homes, businesses, transport and industry switch to electricity. The traditional three-bay Gas Insulated Switchgear (GIS) substation is a proven and reliable way to connect to the 132kV network. Cross Factor is exploring whether, for suitable connections, a simpler approach could deliver the same safe and reliable outcome while requiring less equipment, construction work and time.

Cross Factor aims to introduce a 145kV branch joint as an alternative for suitable connections to UK Power Networks’ 132kV network. Compared with a traditional three-bay GIS substation, it could require less equipment, construction work and land, as well as fewer outages and fewer steps to get the connection up and running.

If successful, Cross Factor will make suitable 132kV connections faster, simpler and cheaper to deliver, while maintaining network safety and reliability.

How we’re doing it

The project will test the branch joint to make sure it is safe, reliable and suitable for use on the 132kV network. The team will first agree what the branch joint needs to do, how it will be tested and the standards it needs to meet. The design will then be reviewed before the branch joint is manufactured.

Once assembled at the testing facility, the branch joint will go through electrical and mechanical testing at 145kV to check that it performs as expected. The results will be recorded and reviewed to confirm whether it meets the agreed safety and performance requirements.

If testing and certification are successful, UK Power Networks will update its engineering standards and guidance so the branch joint can be used on suitable 132kV connection projects as part of normal operations.

What makes it innovative

There are currently no DNO-approved branch joints for use on the 132kV network. Cross Factor will test how this technology could be safely and reliably used at this higher voltage, creating the evidence and engineering guidance needed for future use.

If successful, the solution could make suitable 132kV connections faster, simpler and cheaper to deliver, with less construction work required. This could help UK Power Networks connect more customers efficiently and support the network growth needed for Net Zero.

What we’re learning

During the project, we expect to learn about:

  • Technical performance: Whether the branch joint can operate safely and reliably at 145kV.
  • Testing and approval: What testing and certification are needed before the branch joint can be approved for use.
  • Future use: What engineering standards, guidance and processes are needed for the branch joint to be safely used on suitable 132kV connections as part of normal operations.